A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day ?
A. 18
B. 12
C. 15
D. 14
Answer : C. 15
Explanation:
A’s 2 day’s work = 1/20 x 2
= 1/10
(A + B + C) 1 day’s Work = (1/20 + 1/30 + 1/60)
= 6/60
= 1/10
Now,
Work done in 3 days = (1/10) + (1/10)
= 1/5
Now 1/5 work is done in 3 days.
Now whole work will be done in 3 * 5 = 15 days.
Related Tags
- a b and c can do a piece of work in 15 12 and 20 days,
- a b and c can do a piece of work in 20 24 and 30 days,
- a b and c can do a piece of work in 30 20 and 10 days respectively,
- a b c can do a piece of work in 10 12 and 15 days,
- adani enterpris interview questions and answers,
- adani green energy ltd interview questions and answers,
- adani ports ltd interview questions and answers,
- adani total gas ltd interview questions and answers,
- adani transmission ltd interview questions and answers,
- ambuja cements interview questions and answers,
- apollo hospital interview questions and answers,
- aurobindo pharm interview questions and answers,
- avenue supermarts ltd interview questions and answers,
- axis bank interview questions and answers,
- bajaj auto interview questions and answers,
- bajaj finance interview questions and answers,
- bajaj finserv ltd interview questions and answers,
- balkrishna industries interview questions and answers,
- bandhan bank interview questions and answers,
- berger paints interview questions and answers,
- Bharat Petroleum Corporation Ltd interview questions and answers,
- biocon interview questions and answers,
- britannia industries ltd interview questions and answers,
- cadila health interview questions and answers,
- coal india Ltd interview questions and answers,
- colgate interview questions and answers,
- dabur india ltd interview questions and answers,
- divis labs interview questions and answers,
- dlf interview questions and answers,
- Dr. Reddys Labs interview questions and answers,
- eicher motors ltd interview questions and answers,
- gail (India) Ltd interview questions and answers,
- gland pharma ltd interview questions and answers,
- godrej consumer products ltd interview questions and answers,
- godrej properties interview questions and answers,
- grasim Industries ltd interview questions and answers,
- gujarat gas ltd interview questions and answers,
- havells india ltd interview questions and answers,
- hdfc life insurance company ltd interview questions and answers,
- hero motocorp interview questions and answers,
- hindalco industries ltd interview questions and answers,
- Hindustan Unilever Ltd interview questions and answers,
- hindustan zinc ltd interview questions and answers,
- how to solve time and work problems,
- ICICI Lombard interview questions and answers,
- icici prudential Life Insurance interview questions and answers,
- if 6 men and 8 boys can do a piece of work in 10 days,
- Indian Oil Corporation Ltd interview questions and answers,
- indus towers ltd interview questions and answers,
- indusind bank interview questions and answers,
- interglobe aviation interview questions and answers,
- jsw steel interview questions and answers,
- jubilant foodworks ltd interview questions and answers,
- kotak mahindra bank interview questions and answers,
- L&T Infotech interview questions and answers,
- larsen & toubro Ltd interview questions and answers,
- Lupin interview questions and answers,
- m&m interview questions and answers,
- marico interview questions and answers,
- maruti suzuki interview questions and answers,
- motherson sumi systems interview questions and answers,
- muthoot finance hdfc amc interview questions and answers,
- Nestle interview questions and answers,
- nmdc ltd interview questions and answers,
- ntpc ltd interview questions and answers,
- Oil and Natural Gas Corporation (ONGC) interview questions and answers,
- pi industries ltd interview questions and answers,
- pidilite industries interview questions and answers,
- power grid corporation of India interview questions and answers,
- ril partly paid interview questions and answers,
- sbi card interview questions and answers,
- sbi life insura interview questions and answers,
- shree cements ltd interview questions and answers,
- siemens interview questions and answers,
- srf limited interview questions and answers,
- state bank of India (SBI) interview questions and answers,
- Steel Authority of India Ltd (SAIL) interview questions and answers,
- sun pharma interview questions and answers,
- tata consumer products ltd interview questions and answers,
- tata motors interview questions and answers,
- tata steel interview questions and answers,
- tcs ninja interview questions and answers,
- time and work aptitude tricks,
- time and work basics,
- time and work interview questions and answers,
- time and work problems shortcuts,
- time and work problems tricks,
- time and work problems with solutions,
- titan company interview questions and answers,
- torrent pharma interview questions and answers,
- ultratech cement interview questions and answers,
- United Phosphorus Ltd (UPL) interview questions and answers,
- united spirits interview questions and answers,
- vedanta ltd interview questions and answers,
- zomato interview questions and answers